Removing a load-bearing wall in London: steel beams and RSJ installation

Every open-plan London ground floor is a wall that came out and a beam that went in. The steel is ordered in an afternoon; the propping and the bearings are where the job is won or lost.

  • In-house crew
  • Design and build

Updated September 2026

Removing a load-bearing wall means propping the floors above, cutting the wall out and installing a steel beam, usually an RSJ, on padstones sized by a structural engineer, then having building control inspect it before it is cased in. London cost guides put a single opening at £2,500–£5,000 all in. MO Team designs, props, installs and makes good across London.

What the beam has to do, and what it costs

A wall is load-bearing when something above depends on it: floor joists resting on it, a wall on the floor above continuing its line, a purlin or a chimney breast bearing on it, or the roof ties in the loft. Direction and thickness are clues rather than proof, so we open a small hole and trace the load path before anyone quotes. The work itself has a fixed order. Needles are pushed through the wall above the cut and propped on both sides, the wall comes out, the beam is lifted onto padstones that spread its load into the brickwork below, the gap above it is dry-packed, and only when the packing has cured do the props come out. Building control inspects the beam and its bearings before they are boarded, and the steel is cased to give thirty minutes of fire resistance. London cost guides put an RSJ supplied and fitted at £1,500–£5,000 per beam, of which the steel itself is usually a few hundred pounds (one UK guide puts steel-only at £150–£1,200 depending on size, with a beam of three to five metres at £250–£600); labour, propping and making good are the cost. A single opening with one beam, with the engineer and building control in the price, runs £2,500–£5,000; a through-lounge or a full-width open plan with several beams or a goalpost frame runs £5,000–£15,000.

Three pieces of paper go with the beam. The structural engineer's calculation sizes the section, checks deflection and specifies the padstones; London practices charge £450–£800 for a single beam. Building control is told before work starts, inspects the opening and signs it off with a completion certificate; the London boroughs that publish a clear schedule charge £360–£515 including VAT for a structural opening. Where the beam bears into a wall shared with next door, section 2 of the Party Wall etc. Act 1996 gives you the right to cut in, on a party structure notice served at least two months ahead, on a mid-terrace usually to both neighbours; published London figures put an agreed surveyor's award at £700–£1,800 for each adjoining owner. Planning permission is not needed for an internal wall in an unlisted house, and a flat adds the freeholder's consent to alter.

We do this as structural alterations under one contract, survey to finished opening, calculation and notices included, from one crew, so nobody is standing in your kitchen arguing about whose prop it was. The most common version of the job is opening the back wall for a house extension, the kind of open-plan kitchen our rear extension with a skylight roof in London shows. A breast in the same wall is covered on the chimney breast removal page; for the notice itself, and for a neighbour who dissents, read our party wall agreements in London guide.

What load-bearing wall removal includes

One package: proof of what the wall carries, the calculation, the temporary works, the steel and the finish.

  • Survey and load-path check

    Joist direction, walls above, roof timbers and any previous alterations, confirmed by opening up a patch rather than by guessing from the plaster.

  • Structural calculations and beam design

    The section, the deflection check, the padstones and, where the opening is full width, a goalpost frame, drawn for building control.

  • Building control application and inspections

    Notification before the start, the inspection at the open stage and the completion certificate for your solicitor later.

  • Party wall notices

    Notice drafted and served on every neighbour whose wall takes a bearing, with the two-month period written into the start date.

  • Temporary works

    Needles, props and protection designed as part of the job, so nothing above moves while the wall is out.

  • Steel supply, delivery and installation

    The beam ordered to the engineer's drawing, split and spliced where a terrace hallway will not take it in one piece, lifted and bedded on its padstones.

  • Bearings, packing and fire protection

    Padstones cast or cut in, the gap above the beam dry-packed, and the steel cased in plasterboard for thirty minutes of fire resistance.

  • Making good

    Reveals plastered, the floor made good along the old wall line, skirting and architraves run through, and the disturbed wall decorated.

What is in the price

We handle

  • Survey, calculations and beam drawing
  • Notifying building control and hosting the stage inspections
  • Party wall notices prepared and served
  • Temporary works, propping and protection
  • Steel supply, installation, padstones, packing and fire casing
  • Waste removal and a clean site each day
  • Plastering, floor patching and decorating the disturbed wall

You provide

  • The rooms above and below cleared of furniture along the working route
  • Neighbours' names and addresses for the party wall notices
  • Any existing drawings, certificates or previous survey reports
  • A decision on where the opening sits and whether nibs stay at either end
  • A flat's freeholder consent to alter, where that applies

Not included

  • Fees paid to building control and to party wall surveyors, yours and a neighbour's
  • A new kitchen, floor finishes or joinery in the opened-up space
  • Rewiring or plumbing beyond diverting what runs through the wall
  • Decorating rooms the work did not disturb
  • Glazing or doors in an opened rear wall unless they are quoted with the extension

How it runs

  1. 01

    Prove what the wall carries

    We trace the load path before pricing: which way the joists run, what continues on the floor above, whether a purlin, a chimney breast or a water tank bears on the wall, and what an earlier owner may already have removed. A small opening in the plaster answers more than an hour of guessing.

    You receive
    A sketch of the load path and a list of what the beam has to carry
  2. 02

    Size the beam and the bearings

    Our engineer sizes the steel for the load and the span, checks deflection so the floor above does not bounce, and specifies the padstones. Where the opening runs wall to wall with nothing to bear on, the design becomes a goalpost frame with posts down to new foundations.

    You receive
    Calculations and a beam drawing, including the temporary works sequence
  3. 03

    Book the inspection and serve notice

    We lodge the building control notification and book the inspection, and where the beam bears into a party wall we serve the party structure notice on that neighbour two months or more ahead of the start. We also plan the delivery, because a six-metre beam does not turn a terrace corner and may arrive in two pieces to be spliced on site.

    You receive
    A building control reference, served notices and a delivery plan for the steel
  4. 04

    Prop, cut, lift, pack

    Needles go through the wall above the cut and are propped on both sides, the wall comes out, and the beam is lifted onto its padstones. The gap above is dry-packed and left to cure before the props are struck. Building control inspects the beam, the bearings and the packing before any of it is covered.

    You receive
    Beam in, inspected and photographed, then cased
  5. 05

    Fire-case and finish

    The steel is boxed in plasterboard to the fire rating, the reveals plastered, the floor made good along the line of the old wall and the skirting run through in one length. Your handover pack holds the completion certificate, the calculation and the photographs of the bearings for the day you sell.

    You receive
    A completion certificate and a finished opening

Regulations that apply to removing a load-bearing wall

  • Building Regulations apply to every structural opening

    Removing an internal wall or forming an opening in one is controlled work: building control must know before the start and must see the new structure before anything hides it, and the completion certificate follows.

    Planning Portal: internal walls and building regulations ↗
  • Approved Document A: structure

    Building control measures the finished opening against the calculation: beam size, bearings and padstones. The engineer's design goes in with the notification rather than sitting on file, and the completion certificate records the inspection.

    Approved Document A ↗
  • Bearings and fire protection to the steel

    The Planning Portal's structural-opening guidance says a beam should normally have at least 150 mm of bearing on each side, usually on padstones so the brickwork does not crush, and that a steel beam over an opening should normally be protected to give at least thirty minutes of fire resistance, most often with two or more layers of plasterboard fixed to the manufacturer's specification. An exposed timber beam needs a calculation to show it has that resistance itself.

    Planning Portal: structural opening ↗
  • Party Wall etc. Act 1996, section 2

    Taking the bearing of a beam in a shared wall is one of the section 2 rights. The notice goes to each neighbour whose wall carries a bearing, no later than two months before the start; silence for 14 days counts as a dissent, after which one agreed surveyor or two appointed surveyors produce the award the work is done under.

    Party Wall etc. Act 1996 ↗

Work of this kind

Common questions

Straight answers.

Not answered here?

Tell us what you are planning. We read every enquiry ourselves and reply within one working day.

Ask us directly07424 445105

London cost guides put a single opening with one steel beam at £2,500–£5,000 all in, engineer's calculation, RSJ and building control included, and a through-lounge or a full open-plan ground floor with several beams at £5,000–£15,000. The steel is a small part of either figure; the propping, the labour and the making good are the cost. Add party wall fees where the beam bears into a shared wall. Market ranges from September 2026, not our quotes.