Residential · Loft conversions
Velux loft conversions in London: rooflights, no dormer
The roof keeps its shape. Rooflights go in between the rafters, a new floor and stair go in below them, and the room is insulated, wired and fire-protected. It is the least expensive conversion, and the one that needs the tallest roof to start with.
- Design and build
Updated September 2026
A Velux, or rooflight, loft conversion keeps the existing roof shape and adds rooflights, a new floor, a staircase, insulation and fire protection. It is the least expensive type, needs the most head height, and rarely needs planning permission. Published London guides put it at £30,000–£55,000. MO Team builds Velux conversions as part of its loft work across London.
The conversion that leaves the roof alone
Velux is a brand of rooflight that has become the name for the whole type: a conversion where nothing is added to the outside of the house except windows set into the slope. Inside, the work is the same as any other loft. A new structural floor goes in over the old ceiling joists, usually on steels bearing on the party walls, so the bedroom below does not carry the new room. The rafters are trimmed to take the rooflights, insulation goes between and under them to current standards, a stair rises from the landing below, and the stairwell is fire-protected because the house has gained a storey. What you do not pay for is a dormer or mansard structure, the roofing and cladding that go with it, or, in most cases, a planning application. That is why the published London range starts around £30,000 rather than £55,000.
The catch is head height, and it is a hard one. A dormer creates height where there was none; a rooflight conversion has to find it in the existing roof. About 2.2 metres from the top of the ceiling joists to the underside of the ridge is the working minimum for any loft, and a Velux conversion needs comfortably more than that, because the slope stays on both sides and the standing area is only the strip under the ridge. The steep Victorian and Edwardian roofs across London often have it; shallower 1930s roofs and trussed roofs usually do not, and there a dormer or a hip-to-gable is the honest recommendation even though it costs more. The other limit is floor area you can use: furniture fits under the slope, people do not, so a Velux room is a good bedroom, study or guest room and rarely a second bedroom with a bathroom. Rooflights that project no more than 150 millimetres from the roof plane are permitted development on a house, even at the front; conservation areas and Article 4 directions can still restrict them, and our extension planning guide explains how to check your street for one.
MO Team designs and builds loft conversions across London, and a rooflight conversion is the one we would be most likely to talk you out of, because the tape measure decides it. On the first visit we measure the ridge, look at the rafters and purlins and find where the stair can land; if the height is marginal we say so, and if a dormer would give you a usable room for the extra cost we say that too. Where it does work, it is the quickest and least disruptive loft: no scaffold beyond what the rooflights need, no roof open to the weather, and the stairwell opened last. Our rear dormer loft conversion shows the standard of the floor, the stair and the finish we work to. Loft conversions in London compares all four types, and the loft conversion cost guide sets out typical London prices from published sources.
What a Velux loft conversion includes
One package from the head-height check to the completion certificate, priced against a written specification.
What is in the price
How it runs
- 01
Measure the height and tell you the truth
We measure from the top of the ceiling joists to the underside of the ridge, check whether the roof is cut or trussed, and work out where the stair lands. If a rooflight conversion would leave you crouching, we say so and explain what a dormer would add.
- You receive
- A viability note with the measured height and the honest recommendation
- 02
Design the floor, the rooflights and the stair
The engineer designs the new floor on steels, the rooflight trimming and any purlin changes. Rooflight positions are set for daylight, for an escape-sized opening and for what you will see from the bed rather than for symmetry on the roof.
- You receive
- Building control drawings and structural calculations
- 03
Building control and notices
The building control submission goes in, and party structure notices are served where the steels bear on a party wall. There is usually no planning application, and where a certificate is worth having for a later sale we apply for one.
- You receive
- A submitted application, served notices and a start date
- 04
Floor, rooflights and insulation
Steels and joists go in over the old ceiling, the rafters are trimmed and the rooflights fitted and flashed in a day or two each, then the insulation, ventilation and boarding to the slopes and ceiling. The roof is never open, so the weather rarely stops the job.
- You receive
- A boarded, insulated room with inspection records
- 05
Stair, services and sign-off
The stair opening is cut last, the flight fitted, fire doors and alarms installed, electrics and heating completed, plastering and decoration done. Building control signs off and the certificates are handed over as one pack.
- You receive
- Completion certificate, electrical certificates and rooflight warranties
Regulations that apply to a rooflight conversion
Work of this kind


Pop Mart, Trafford Centre
- Type
- Brand rollout

Related
Services
Further reading
Common questions
Straight answers.
Not answered here?
Tell us what you are planning. We read every enquiry ourselves and reply within one working day.
Ask us directly07424 445105Published London guides for 2026 put a Velux or rooflight conversion at £30,000–£55,000. That is the median of several companies' ranges, not our quote; the sources disagree on what a basic conversion includes, and some quote with VAT while others do not. Building control fees, any party wall surveyor and the decoration below come on top. Our loft conversion cost guide lists the sources, and the same page shows why a dormer starts at £55,000.
A Velux conversion is the only type where that figure is even close, and in London at 2026 prices the published range still starts at £30,000. The advertised starting prices below that describe a floor, a rooflight and a ladder, without the stair, the fire doors on the floors below or the insulation to current standards; the loft conversion cost guide sets out what each type costs and why, and boarding a loft for storage is the honest use of a smaller budget.
Since 25 April 2024, building work done without planning permission in England becomes immune from enforcement only after ten years; work substantially completed before that date keeps the old four-year limit (gov.uk planning enforcement guidance, checked September 2026), so check the position with your council. A rooflight conversion rarely needs planning permission anyway, so the rule seldom applies to it; Building Regulations approval is the requirement that matters here, and it has no time limit for a conversion that was never inspected. Our loft conversion cost guide covers the rule in full.
Usually not on a house. Rooflights that project no more than 150 millimetres from the roof surface and sit below the ridge are permitted development, including on the front slope, and side-facing ones simply have to be obscure-glazed and non-opening below 1.7 metres. Conservation areas and Article 4 directions can restrict rooflights on the street-facing slope, listed buildings need consent for any of them, and flats have no permitted development rights (Planning Portal, loft conversions, checked September 2026; confirm with your borough). We check the address before recommending positions.
More than for any other type. About 2.2 metres from the top of the ceiling joists to the underside of the ridge is the working minimum for a loft conversion, and a rooflight conversion needs comfortably above it, because the new floor, insulation and plasterboard take around 300 millimetres and the slope stays on both sides. Steep Victorian and Edwardian roofs often have it; shallow 1930s and trussed roofs usually do not, and there a dormer is the honest answer.
If the roof is tall, a Velux conversion is the best value loft there is: no roof structure, no cladding, usually no planning, and the least disruption. If the standing area under the ridge would be a narrow strip, it is money spent on a room you cannot furnish, and a dormer at £55,000–£80,000 in the published London ranges buys a bedroom you can stand up in across most of its floor. We measure and tell you which applies before drawing anything.
Yes, whether or not planning permission is needed. The new floor, the trimming of the rafters for the rooflights, insulation, the stair, ventilation and the fire strategy for the whole house are all controlled, and the work is inspected as it proceeds. Fitting a rooflight into an existing roof without converting the loft is a smaller matter, but the moment there is a floor and a stair it is a conversion, and the completion certificate is what makes it a room.
With no roof structure to build and usually no planning application, the building control submission is normally the only approval in front of the start; where the steels bear on a party wall, the two-month notice period runs first, so we serve notices at design stage. On site it is the shortest loft programme, because the roof is never opened and the weather rarely delays it, and a small shower room or a trussed roof that needs extra steel adds to it. We give the on-site programme for your roof with the quotation.
Yes, if it is built as one: a structural floor, a stair with compliant headroom, fire doors and alarms making the stairwell a protected route, insulation to current standards and a building control completion certificate at the end. A loft reached by a ladder, or a floor laid on the old ceiling joists, is storage whatever furniture is in it. Estate agents and surveyors describe rooms by their paperwork, not their bed.
Usually, and it is a common second step. The floor, the stair and the fire protection are already there, so the later job is the dormer structure itself: the rear slope is opened, the box framed and clad, and the room replanned around the new flat ceiling. Steels sized for the first conversion may need checking for the added weight, and party wall notices apply again. It costs more in total than building the dormer first, but it lets the budget arrive in two parts.
Is your roof tall enough for a Velux conversion?
Measure from the top of the ceiling joists to the underside of the ridge and send it with a photo of the loft. We will tell you straight away whether a rooflight conversion works or whether a dormer is the better use of the money.